PACIFIC PALISADES, Calif. — Construction resumed in April 2026 on the Sunset Boulevard Distribution System Corridor — the backbone conduit that will carry new 34.5kV and 12kV lines feeding Distribution Station 29.
Work started near Fire Station 69 moving east, keeping one lane open each direction. Neighborhood undergrounding cannot begin until the 12kV backbone is complete, currently estimated for the third quarter of 2026, starting in the Alphabet Streets.